In mid-2025, together with our partners from Tehnounion, we took over the role of supplier of Motor Control Centers (MCC) for the client MVM Južna Bačka, for the needs of the trigeneration plant at the EXPO complex.
The MCC systems were delivered in mid-September 2025.
General:Construction of a trigeneration plant for the supply of heating, cooling and electrical energy to facilities within the PPPPN National Football Stadium complex.
Investor: PE “Belgrade District Heating Plants” Belgrade and the Ministry of Finance
Description:Motor Control Centers (MCC) – Siemens Sivacon S8, in accordance with SRPS IEC 61439-1/2 standard.
A total of 59 panels distributed across 8 MCC line-ups:
- 3 MCCs with rated current of 2500 A
- 2 MCCs with rated current of 1600 A
- 3 MCCs with rated current of 1280 A